Design and equipment:
High efficiency chiller, water pump and heat and cold recovery system, combined with intelligent control system to achieve energy saving operation.
Phase I plant:
One 600RT maglev centrifuge, one 600RT variable frequency water-cooled centrifugal unit and multi-typhoon cold module cold and hot water unit.
Second plant:
One 800RT maglev centrifuge, one 800RT variable frequency water-cooled centrifugal unit and four-control air-cooled module cold and hot water unit.
property:
24-hour cooling and heating throughout the year, energy efficiency ratio of 5.0, more than 40% energy saving than the traditional system.
Distributed photovoltaic:
Installed capacity:
The total installed capacity of the first and second phase plant is about 1.6MWp, and the annual power generation is about 1.68,000,000 KWh.
Environmental benefit:
It saves about 605 tons of standard coal and reduces carbon dioxide emissions by about 1675 tons per year.
Location and scale:
Located in the southwest corner of the Phase II plant, it contains two 1MWh container energy storage power stations
Economic benefit:
By cutting peaks and filling valleys, it is expected to save electricity costs of about 550,000 yuan per year.